Two distressed sovereign offtakers sharing one asset. GE/PowerChina consortium terminated in 2022.
Zambia
Drought exposed hydro concentration risk; the copper-corridor build-out is the counterweight.
Continental average 37.13
3.8 GW installed
108 registry projects
Estimated investment requirement
AIDI trajectory 2015—2025
Commitments vs disbursement, $bn
Infrastructure sub-indices
Project register · 10 tracked (loading)
| Project | Sector | Value | Status | Target |
|---|---|---|---|---|
Batoka Gorge Hydro Scheme Two distressed sovereign offtakers sharing one asset. GE/PowerChina consortium terminated in 2022. | Hydro | $5bn | Feasibility | 2033 |
Lobito Atlantic Railway The flagship Western counter-offer to Chinese resource-corridor finance. Copper and cobalt to the Atlantic. | Rail | $2.3bn | Construction | 2027 |
Mingomba Copper Project AI-led exploration validated by drilling; the first serious Western greenfield copper bet in Zambia in decades. | Mine | $2bn | Feasibility | 2031 |
TAZARA Rehabilitation Concession Fifty years after construction, the original Chinese railway diplomacy asset is being recapitalised. | Rail | $1.4bn | Structuring | 2029 |
Walvis Bay Corridor Logistics Hub Underused capacity looking for cargo; the corridor's problem is demand, not concrete. | Ports + corridor | $0.7bn | Structuring | 2029 |
Umoja Fibre Route (Google) The first intercontinental route to run overland through the African interior rather than around it. | Terrestrial + subsea | $0.6bn | Construction | 2027 |
Kolwezi Battery Precursor Plant The beneficiation test case: whether battery value-add can be retained at source. | Processing | $0.4bn | Feasibility | 2029 |
Zambia Scaling Solar Round II The Scaling Solar template works; ZESCO's balance sheet is the binding constraint. | Solar PV | $0.3bn | Structuring | 2027 |
LEO Satellite Backhaul Rollout Regulatory approval, not capital, determines the map. Licensing has moved faster than any fibre programme. | Satellite | $0.3bn | Operational | 2025 |
Kariba Dam Rehabilitation Plunge-pool reshaping to prevent failure of a dam carrying 40% of two countries' generation. | Dam safety | $0.3bn | Construction | 2026 |
The flagship Western counter-offer to Chinese resource-corridor finance. Copper and cobalt to the Atlantic.
AI-led exploration validated by drilling; the first serious Western greenfield copper bet in Zambia in decades.
Fifty years after construction, the original Chinese railway diplomacy asset is being recapitalised.
Underused capacity looking for cargo; the corridor's problem is demand, not concrete.
The first intercontinental route to run overland through the African interior rather than around it.
The beneficiation test case: whether battery value-add can be retained at source.
The Scaling Solar template works; ZESCO's balance sheet is the binding constraint.
Regulatory approval, not capital, determines the map. Licensing has moved faster than any fibre programme.
Plunge-pool reshaping to prevent failure of a dam carrying 40% of two countries' generation.